A, B and C can do a work in 36 days. A and B together can do twice as much work as C alone and A and C together can do thrice as much work as B alone. In how many days can alone C finish the work ?

time and work

  • Shalini
  • 02 दिसम्बर
  • 64379 दृश्य
  • 4 उत्तर
Your Answer

1 day work for (A+B+C) = 1/36 ............(ii)
Now, (A+B) = 2C ..........................(i)

From (i)and(ii): 3C = 1/36
C = 1/108

Thus, C takes 108 days to complete the whole work alone.