If 3 men can finish their work for 8 days, then how many men are needed to finish their work in 6 days? a) 5 Men b) 4 Men c) 8 Men d) None of these
- 19290 दृश्य
- 381 उत्तर
381 उत्तर
- If a man rows at 6 km/h in still water and 4.5 km/h against the current, then his along the current is?
- What is a Smart Value company in India?
- is there general knowledge questions in SBI prelims
- How was your SBI PO Prelims 2017 Result?
- What Is The Starting Sary Of Sbi PO And How It Is Incremented Over The Years And What Is The Final Salary???
- How many vacancies are there for SBI PO?
- prelims ke admit card aa gye kya
- SBI PO PRELIMS EXAM PATTERN SBI PO PRELIMS EXAM PATTERN
- R S agrawal book is best for banking?
- which best book for exam of preliminary exam
मॉक परीक्षण अभ्यास के लिए
sbi po prelim exam
Number of men * 6 days = 24 man-daysbr /br /Now, solve for the number of men:br /br /Number of men = 24 man-days / 6 days = 4 menbr /br /So, the answer is (b) 4 Men