Quantitative Aptitude, Time and work
A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternatively, A beginning, in how many days, the work will be completed?
- 3541 दृश्य
- 1 उत्तर
1 उत्तर
-
-
- 29 अप्रैल
- 2 टिप्पणी
-
- how many 5 digits can be formed by the given digits
- What is the difference between attitude and aptitude?
- There is very few questions of probability here. Kindly give some more questions.
- What are aptitudes examples? Expalin your answer
- Raju has 14 currency notes in his pocket consisting of only Rs. 20 notes and Rs. 10 notes. The total money values of the notes is Rs. 230. The number of Rs. 10 notes that Raju has is (A) 5 (B) 6 (C) 9
- Quantitative Aptitude
Simplification
- Complete the sentence: Dare .................. mistakes.
- If 137 + 276 = 435 how much is 731 + 672 ?
- 25 persons are in a room 15 of them play hockey..................
- Kindly add aptitude problems on Progressions
मॉक परीक्षण अभ्यास के लिए
aptitude
10 1/4 Days.. Please reply if It's Wrong