A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternatively, A beginning, in how many days, the work will be completed?
- 3539 Views
- 1 Answers
1 Answers
-
-
- 29 Apr
- 2 Comment
-
- Which book is best for quantitative aptitude?
- Which of the following options is the closest in meaning to the word below ?
- What is the value of b+c-a if...
- What are the topics in verbal reasoning? Explain your answer
- The question below consist of a pair of related words followed by four pairs of words. Select the pair that best expresses
- Quantitative Aptitude
Simplification
- There is very few questions of probability here. Kindly give some more questions.
- How to prepare for Cocubes test in appti?
- Raju has 14 currency notes in his pocket consisting of only Rs. 20 notes and Rs. 10 notes. The total money values of the notes is Rs. 230. The number of Rs. 10 notes that Raju has is (A) 5 (B) 6 (C) 9
- 25 persons are in a room 15 of them play hockey..................
Practice Mock Test
aptitude
10 1/4 Days.. Please reply if It's Wrong