SBI PO Prelim Exam Question
If 3 men can finish their work for 8 days, then how many men are needed to finish their work in 6 days? a) 5 Men b) 4 Men c) 8 Men d) None of these
- 16068 Views
- 381 Answers
-
-
- 15 Apr
- 0 Comment
-
-
Ans: 4 Men. Explanation:::: 3 men completes 1/8 th of work each day. So 1 individual man can do (1/8)/3=(1/24) work per day. Similarly, In order to complete the work in 6 days. "x" no. of men need to complete 1/6th of work per day. So, 1 man completes (1/6x)th work per day. As the work power for each individual man i.e., portion of work completed per day by each man is same or equal. We can derive as (1/24)th work/day/man= (1/6x)th work/day/man. = x= 4. So 4 men can complete the same work in 6 days. Assuming each man has ideally same work power.
-
- 02 Feb
- 0 Comment
-
- can we do rough work while giving test?
- date of prilim exam?
- Is there any changes in exam pattern of SBI PO Prelim?
- Pranay:
- how can I stop that sound that comes after attending a question,??
- what is the time to give online exam in mobile
- What is the basic salary of SBI PO?
- give me tricks to manage time
- I'm? not able to view the SBI po prelims result
the captcha image is not visible
- sir prelims exam dates will be announced on?
b