SBI PO Prelim Exam Question
If 3 men can finish their work for 8 days, then how many men are needed to finish their work in 6 days? a) 5 Men b) 4 Men c) 8 Men d) None of these
- 19641 Views
- 381 Answers
381 Answers
-
-
- 14 Mar
- 0 Comment
-
- ans plz ....
- can we crack the exam within 2months of preparations ?
- how to prepare English language
- Time and work question
- syllabus
- I'm? not able to view the SBI po prelims result
the captcha image is not visible
- SBI Prem Practice
- IBPS PO Interview
- what % is marks required for PO 2016?
- do we have to attest the photocopy of identity proof by gazette officer or we have to self attest it? plz reply ASAP
Practice Mock Test
sbi po prelim exam
4 men