SBI PO Prelim Exam Question

If 3 men can finish their work for 8 days, then how many men are needed to finish their work in 6 days? a) 5 Men b) 4 Men c) 8 Men d) None of these

  • Sweety
  • 12 अक्तूबर
  • 19273 दृश्य
  • 381 उत्तर
Your Answer

Men Inversely Proportional To Day Men1=3. Men2=_ Day1=8. Day2=6 Men1*day1=men2*day2 3*8=men2*6 Men2=24/6 Men2=4 answer

0
sbi po prelim exam
मॉक परीक्षण अभ्यास के लिए
sbi po prelim exam