A is twice as good as B.working together if they can do a work in 60 days.In how many days they are going to do the work?

Time and work

  • Shanmugan
  • 25 जुलाई
  • 5345 दृश्य
  • 11 उत्तर
Your Answer

If A takes 10 days to complete a work means A's one day work is 1/10 so complete this work A takes 10/1 days is same as 10 days Sat the same way (A + B)'s 1 day's work 2/45 means They will take 45/2 = 22 1/2 days