If 3 men can finish their work for 8 days, then how many men are needed to finish their work in 6 days? a) 5 Men b) 4 Men c) 8 Men d) None of these
- 19280 Views
- 381 Answers
381 Answers
- утепление балкона фото
- give me tricks to manage time
- A help
- 15 min reading time?
- which book is the best for the preparation of banking and finance
- I want a best book for SBI po post .. can anyone suggest book name
- when is the results for the SBI PO PRELIMINARY???
- What is the percentage required in graduation for bank po?
- IBPS PO Interview
- can we do rough work while giving test?
Practice Mock Test
sbi po prelim exam
Number of men * 6 days = 24 man-daysbr /br /Now, solve for the number of men:br /br /Number of men = 24 man-days / 6 days = 4 menbr /br /So, the answer is (b) 4 Men