Question from aptitude for Unisys.

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men work to complete the job? (a) 8 hrs (b) 7 1/2 hrs (c) 7 hrs (d) 9 hrs (e) none of these options

  • Shreya
  • 1552 Views
  • 2 Answers
2 Answers
  • good job! well done


  • strongAnswer is option (e)/strongbr /br /strongExplanation: /strongbr /br /?30 * 20 * 9 = 5400 man-hours required to complete the jobbr /:br /Let x = no. hrs a day to do the same job (assuming in 20 days)br /40 * 20 * x = 5400br /800x = 5400br /br /x = 5400/800br /br /x = strong6.75 hrs/strong a day for 20 days to do the same job