Close sidebar

Quantitative Aptitude, Time and work

A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternatively, A beginning, in how many days, the work will be completed?

  • Seshathri
  • 3235 Views
  • 1 Answers
1 Answers
  • 10 1/4 Days.. Please reply if It's Wrong


Practice Mock Test
aptitude