A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternatively, A beginning, in how many days, the work will be completed?
- 3244 Views
- 1 Answers
1 Answers
-
-
- 29 Apr
- 2 Comment
-
- If 137 + 276 = 435 how much is 731 + 672 ?
- Complete the sentence: Dare .................. mistakes.
- How to improve my calculations?
- Shahid had a certain number of Re 1 coins, Rs 2 coins and Rs 10 coins. If..
- If the number 3072 is divisible by both 6 and 8, find
- What type of questions are asked in Varroc Online campus placements test?
- What are the best books for aptitude test preparations?
- Profit and loss selling price given and need to find the printed price
- What is the difference between attitude and aptitude?
- 30% of the men are more than 25 years old and ....
Practice Mock Test
aptitude
10 1/4 Days.. Please reply if It's Wrong